East High Street Improvement Project

WHAT’S EXPECTED THIS WEEK

Week of August 12th – Work will continue on the installation of storm sewer facilities.  In addition, work replacing water service lines to new curb stops will begin.  Street closures, including access to Queen Street, and Queen Street crossing East High Street, are expected during working hours to allow equipment and personnel safe working conditions.

Week of August 5th – Contractor should be completed with removing/replacing sanitary sewer laterals.  Work will start for the installation of storm sewer facilities.  Street closures, including access to Queen Street, and Queen Street crossing East High Street, are expected during working hours to allow equipment and personnel safe working conditions.

Week of July 22nd – Contractor is continuing the process of removing/replacing sanitary sewer laterals.  Street closures, including access to Queen Street, and Queen Street crossing East High Street, are expected during working hours to allow equipment and personnel safe working conditions.

Week of June 24th – UGI Utility is scheduled to continue work relocating gas lines in areas of conflict with other public utilities.  Street closures are expected during working hours to allow equipment and personnel safe working conditions.

Week of June 10th – Work will continue on lining the existing sanitary sewer main.  Contractor will be begin working at the square and will be working eastward toward Queen Street.  Residents are reminded to remove vehicles from the street to allow for construction.  Street closures are expected during working hours.

Week of June 3rd – Work is expected to begin on lining the existing sanitary sewer main located in the street on Wednesday.  Street closures are expected during working hours to allow equipment and personnel safe working conditions.

Week of May 27th – The removal of street trees along East High Street signals the start of street improvements.  During working hours, vehicle traffic will be limited and, at times, prohibited on East High Street between the square in Maytown and the fire station of the Maytown East Donegal Township Fire Department.


Project Emergency Contact Numbers

Road Work Issues – Jake Bair 717-604-4309

Public Water Issues – Don Richards 717-203-5581 or Tim Richards 717-203-4845

Public Sewer Issues – Joyce Boyer 717-426-2855

 


March 26, 2019

BID OPENING RESULTS

MacMor Construction – $1,022,215.75

Construction Masters Services, LLC – $1,249,355.70

Shiloh Paving Excavating Inc. – $1,279,775.95

Doug Lamb Construction, Inc. – $1,509,194.00

Pennsy Supply Inc. – $1,549,815.85

Farhat Excavating, LLC – $1,591,805.00


To view project construction drawings, please click on thumbnails below.

East High Street – Maytown Square to Taylor Street

East High Street – Taylor Street to Queen Street

East High Street – Queen Street to Apple Alley

East High Street – Apple Alley to Union Cemetery

Street Tree Handout